The progress of works in plot M78

The progress of works in Marota City Executing the fourth basement roof casting works in the M78 Plot

The progress of works in plot B130

The progress of works in Marota City Executing the eighth floor casting works in the B130 Plot

Tower T100

The design for the Tower T100 has get the approval of the technical committee which is authorized to study the initial buildings designs in Marota city.

The progress of works in plot B130

The progress of works in Marota City Executing the seventh floor casting works in the B130 Plot

Issuance of the necessary permit to start construction work for plot B124

The progress of works in Marota City Permit issued to start construction work for B124 in Marota City The Tower consists of: A reception a children's playroom in ground floor, two technical floors,...

Postponing the start date of the workshop

The start date of the training workshop (Establishing, dissolving and liquidation companies) at Faculty of Law is postponed. To start on Monday, /9August/ 2021 instead of Sunday This is because of the...